With the distribution and insertion of 53,000 new ties on the 62 miles of Northwestern Pacific mainline between Lombard and Windsor complete, Balfour Beatty forces turned their attention to ballasting last week. During the next two to three weeks, approximately 22,000 tons of rock from the Syar Industries quarry in Napa will be dumped and the mainline will be tamped between Lombard and Ignacio.