NCRA/Harbor district project not approved by CTC
Friday 11 Apr 2008, 09:30
Filed under: Humboldt, NCRA, Railroad | Tags:

Thanks to Mike B for pointing it out.

22 HUM

Northern California
Freight Corridor
Restoration Project
Rehabilitate Northern
Corridor of the NWP
railroad from the Port of
Humboldt Bay to South
Fork, and implement
sediment control strategies
from the Humboldt Bay to
reduce shoaling at its
entrance.

I

1. Scope of Work unclear – two different
types of projects merged into one
nomination.
2. Project implementing agency unclear.
3. Air Quality impacts require further
analysis. Required analysis not
provided. Need project
documentation related to emissions.
4. 1:1 Match Screen not met – Match
proposed depends on unsecured loan
from FRA.
5. Delivery schedule is questionable.
Overlapping environmental, design
and construction phases.
1. Unresolved – Scope of Work includes
two different types of projects (Rail
extension and channel dredging)
merged into one nomination.
Should have been nominated as two
separate projects.
2. Unresolved – Implementing Agency to
be NCRA with an MOU between
NCRA and HBHD.
3. Un-resolved – Air Quality impacts
require further analysis. Per agency
note, project documentation is not
available pertaining to emission
impacts.
4. Unresolved – 1:1 Match not met –
Match proposed depends on
unsecured loan from FRA.
5. Unresolved – Delivery schedule is
questionable. Overlapping
environmental, design and